Pipe Organ Installation Update Dec. 11, 2023

On Dec. 6 Otto provided an update with the installation schedule for the pipe organ.

Dec. 11-12 Upper “outside” case and pedal wood pipes installed, shortly after the facade will be installed.
Dec. 13 The main chest should be ready for “blow out” (magnet exercising and dust/debris removal), the leak check will follow.
Dec. 15 The metal “inside” pipes install.
Dec. 16 Initial tuning, playable and ready for practice
Dec. 21 ready for service.

Thank you Otto for your continued dedication.